Original Cost
₹499 Cr
Baseline estimate
Revised Cost
₹499 Cr
Latest approved cost
Expenditure
₹207 Cr
Spent to date
Utilization
41.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹292 Cr
Budget left
Spent
₹207 Cr
Remaining
₹292 Cr
Total
₹499 Cr
Project Approved
Construction / Implementation
Original End Date
13/07/2024
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹499 Cr — no cost escalation recorded.
Expenditure stands at ₹207 Cr, which is 41.4% of the revised project cost.
Remaining budget: ₹292 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.