Original Cost
₹322 Cr
Baseline estimate
Revised Cost
₹322 Cr
Latest approved cost
Expenditure
₹214 Cr
Spent to date
Utilization
66.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹108 Cr
Budget left
Spent
₹214 Cr
Remaining
₹108 Cr
Total
₹322 Cr
Project Approved
Construction / Implementation
Original End Date
01/02/2026
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹322 Cr — no cost escalation recorded.
Expenditure stands at ₹214 Cr, which is 66.5% of the revised project cost.
Remaining budget: ₹108 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.