Aviation & Aviation InfrastructureIPM · Central Project#612788

Construction of New Domestic Terminal Building and Miscellaneous Works at Belagavi Airport.

Ministry of Civil AviationKarnataka
Revised Cost: ₹322 CrUtilization: 75.2%

Original Cost

₹322 Cr

Baseline estimate

On budget

Revised Cost

₹322 Cr

Latest approved cost

Expenditure

₹242 Cr

Spent to date

Utilization

75.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹80 Cr

Budget left

Budget Utilization

75.2%
0%25%50%75%100%

Spent

₹242 Cr

Remaining

₹80 Cr

Total

₹322 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/02/2026

Revised Completion

15/09/2026

Completed

Project Details

Project Code612788
SectorAviation & Aviation Infrastructure
MinistryMinistry of Civil Aviation
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹322 Cr
Revised Cost₹322 Cr
Expenditure₹242 Cr
Original End Date01/02/2026
Revised Date15/09/2026

Project Intelligence

Project is within original budget of ₹322 Cr — no cost escalation recorded.

Expenditure stands at ₹242 Cr, which is 75.2% of the revised project cost.

Remaining budget: ₹80 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.

Construction of New Domestic Terminal Building and Miscellaneous Works at Belagavi Airport. is a centrally-funded infrastructure project under Ministry of Civil Aviation, in the Aviation & Aviation Infrastructure sector. The original approved cost is ₹322.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of New Domestic Terminal Building and Miscellaneous Works at Belaga"?
Construction of New Domestic Terminal Building and Miscellaneous Works at Belagavi Airport. is a centrally-funded infrastructure project under the Ministry of Civil Aviation, tracked through the Investment Project Monitoring (IPM) system. Sector: Aviation & Aviation Infrastructure. State: Karnataka. Original cost: ₹322 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹322 Cr has not been significantly revised. Expenditure: ₹242 Cr (75.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of New Domestic Terminal Building and Miscellan is under the Ministry of Civil Aviation in the Aviation & Aviation Infrastructure sector. Project code: 612788. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Domestic Terminal Building and Miscellan is one of several Bihar projects tracked under the Aviation & Aviation Infrastructure sector on the IPM system.