Original Cost
₹19.0K Cr
Baseline estimate
Revised Cost
₹19.0K Cr
Latest approved cost
Expenditure
₹20 Cr
Spent to date
Utilization
0.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹19.0K Cr
Budget left
Spent
₹20 Cr
Remaining
₹19.0K Cr
Total
₹19.0K Cr
Project Approved
Construction / Implementation
Original End Date
12/12/2029
Revised Completion
Completed
Mega infrastructure project worth ₹19.0K Cr — among the largest central projects in Gujarat.
Project is within original budget of ₹19.0K Cr — no cost escalation recorded.
Expenditure stands at ₹20 Cr, which is 0.1% of the revised project cost.
Remaining budget: ₹19.0K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.