Electricity GenerationIPM · Central Project +19.7% overrun#602194

Khurja super Thermal Power Plant [2X660 MW]

Ministry of PowerUttar Pradesh
Revised Cost: ₹13.3K CrUtilization: 97.6%Overrun: +₹2187 Cr

Original Cost

₹11.1K Cr

Baseline estimate

+20% overrun

Revised Cost

₹13.3K Cr

Latest approved cost

Expenditure

₹13.0K Cr

Spent to date

Utilization

97.6%

Of revised budget

Escalated

Cost Status

+19.7%

+₹2187 Cr increase

Remaining

₹324 Cr

Budget left

Budget Utilization

97.6%
0%25%50%75%100%

Spent

₹13.0K Cr

Remaining

₹324 Cr

Total

₹13.3K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹11.1K Cr

Revised Cost

₹13.3K Cr

Increase

+₹2187 Cr

Escalation

+19.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/02/2024

Revised Completion

30/09/2025

Completed

Project Details

Project Code602194
SectorElectricity Generation
MinistryMinistry of Power
StateUttar Pradesh
Data Month2025-11

Financial Summary

Original Cost₹11.1K Cr
Revised Cost₹13.3K Cr
Expenditure₹13.0K Cr
Original End Date02/02/2024
Revised Date30/09/2025

Project Intelligence

Mega infrastructure project worth ₹13.3K Cr — among the largest central projects in Uttar Pradesh.

Cost has increased by ₹2187 Cr (19.7%) from the original estimate of ₹11.1K Cr.

Expenditure stands at ₹13.0K Cr, which is 97.6% of the revised project cost.

Remaining budget: ₹324 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Electricity Generation. Ministry: Ministry of Power.

Khurja super Thermal Power Plant [2X660 MW] is a centrally-funded infrastructure project under Ministry of Power, in the Electricity Generation sector. The original approved cost is ₹11089.00 Cr, later revised to ₹13276.20 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Khurja super Thermal Power Plant [2X660 MW]"?
Khurja super Thermal Power Plant [2X660 MW] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Electricity Generation. State: Uttar Pradesh. Original cost: ₹11089 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹11089 Cr and has been revised to ₹13276 Cr — a cost overrun of +19.7%. Expenditure to date: ₹12952 Cr (97.6% of revised cost). Data as of 2025-11.
QWhich ministry is responsible for this project?
Khurja super Thermal Power Plant [2X660 MW] is under the Ministry of Power in the Electricity Generation sector. Project code: 602194. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Khurja super Thermal Power Plant [2X660 MW] is one of several Bihar projects tracked under the Electricity Generation sector on the IPM system.