Inter-regional [NR-WR] Transmission System strengthening to relieve the loading of 765 kV Vindhyachal-Varanasi D/c line
Original Cost
₹2368 Cr
Baseline estimate
Revised Cost
₹2368 Cr
Latest approved cost
Expenditure
₹166 Cr
Spent to date
Utilization
7.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2202 Cr
Budget left
Budget Utilization
7.0%Spent
₹166 Cr
Remaining
₹2202 Cr
Total
₹2368 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/10/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2368 Cr — no cost escalation recorded.
Expenditure stands at ₹166 Cr, which is 7.0% of the revised project cost.
Remaining budget: ₹2202 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Inter-regional [NR-WR] Transmission System strengthening to relieve the loading of 765 kV Vindhyachal-Varanasi D/c line is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹2368.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Inter-regional [NR-WR] Transmission System strengthening to relieve the loading "?
- Inter-regional [NR-WR] Transmission System strengthening to relieve the loading of 765 kV Vindhyachal-Varanasi D/c line is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Uttar Pradesh. Original cost: ₹2368 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹2368 Cr has not been significantly revised. Expenditure: ₹166 Cr (7.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Inter-regional [NR-WR] Transmission System strengthening to is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617807. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Inter-regional [NR-WR] Transmission System strengthening to is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.