Original Cost
₹1037 Cr
Baseline estimate
Revised Cost
₹1106 Cr
Latest approved cost
Expenditure
₹1134 Cr
Spent to date
Utilization
102.5%
Of revised budget
Cost Status
+6.7%
+₹69 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹1134 Cr
Remaining
₹0 Cr
Total
₹1106 Cr
Original Cost
₹1037 Cr
Revised Cost
₹1106 Cr
Increase
+₹69 Cr
Escalation
+6.7%
Project Approved
Construction / Implementation
Original End Date
22/01/2024
Revised Completion
31/05/2026
Completed
Cost has increased by ₹69 Cr (6.7%) from the original estimate of ₹1037 Cr.
Expenditure stands at ₹1134 Cr, which is 102.5% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Electricity Generation. Ministry: Ministry of Power.