Original Cost
₹1549 Cr
Baseline estimate
Revised Cost
₹1549 Cr
Latest approved cost
Expenditure
₹481 Cr
Spent to date
Utilization
31.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1068 Cr
Budget left
Spent
₹481 Cr
Remaining
₹1068 Cr
Total
₹1549 Cr
Project Approved
Construction / Implementation
Original End Date
07/03/2027
Revised Completion
06/03/2027
Completed
Project is within original budget of ₹1549 Cr — no cost escalation recorded.
Expenditure stands at ₹481 Cr, which is 31.1% of the revised project cost.
Remaining budget: ₹1068 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.