Original Cost
₹1305 Cr
Baseline estimate
Revised Cost
₹1551 Cr
Latest approved cost
Expenditure
₹923 Cr
Spent to date
Utilization
59.5%
Of revised budget
Cost Status
+18.9%
+₹246 Cr increase
Remaining
₹628 Cr
Budget left
Spent
₹923 Cr
Remaining
₹628 Cr
Total
₹1551 Cr
Original Cost
₹1305 Cr
Revised Cost
₹1551 Cr
Increase
+₹246 Cr
Escalation
+18.9%
Project Approved
Construction / Implementation
Original End Date
30/06/2026
Revised Completion
30/09/2026
Completed
Cost has increased by ₹246 Cr (18.9%) from the original estimate of ₹1305 Cr.
Expenditure stands at ₹923 Cr, which is 59.5% of the revised project cost.
Remaining budget: ₹628 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.