Original Cost
₹593 Cr
Baseline estimate
Revised Cost
₹593 Cr
Latest approved cost
Expenditure
₹551 Cr
Spent to date
Utilization
93.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹42 Cr
Budget left
Spent
₹551 Cr
Remaining
₹42 Cr
Total
₹593 Cr
Project Approved
Construction / Implementation
Original End Date
31/08/2026
Revised Completion
31/08/2024
Completed
Project is within original budget of ₹593 Cr — no cost escalation recorded.
Expenditure stands at ₹551 Cr, which is 93.0% of the revised project cost.
Remaining budget: ₹42 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.