NITPatna
Original Cost
₹499 Cr
Baseline estimate
Revised Cost
₹499 Cr
Latest approved cost
Expenditure
₹450 Cr
Spent to date
Utilization
90.2%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹49 Cr
Budget left
Spent
₹450 Cr
Remaining
₹49 Cr
Total
₹499 Cr
90.2%
Utilized
Project Approved
Construction / Implementation
Original End Date
2024-07-31
Revised Completion
2026-01-31
Completed
Project is within original budget of ₹499 Cr — no cost escalation recorded.
Expenditure stands at ₹450 Cr, which is 90.2% of the revised project cost.
Remaining budget: ₹49 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.