Original Cost
₹68 Cr
Baseline estimate
Revised Cost
₹264 Cr
Latest approved cost
Expenditure
₹27 Cr
Spent to date
Utilization
10.4%
Of revised budget
Cost Status
+288.1%
+₹196 Cr increase
Remaining
₹237 Cr
Budget left
Spent
₹27 Cr
Remaining
₹237 Cr
Total
₹264 Cr
Original Cost
₹68 Cr
Revised Cost
₹264 Cr
Increase
+₹196 Cr
Escalation
+288.1%
Project Approved
Construction / Implementation
Original End Date
31/07/2026
Revised Completion
31/03/2027
Completed
Cost has increased by ₹196 Cr (288.1%) from the original estimate of ₹68 Cr.
Expenditure stands at ₹27 Cr, which is 10.4% of the revised project cost.
Remaining budget: ₹237 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.