CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHASE 1A

Department of Higher EducationKerala
Revised Cost: ₹1217 CrUtilization: 58.1%Overrun: +₹211 Cr

Original Cost

₹1006 Cr

Baseline estimate

+21% overrun

Revised Cost

₹1217 Cr

Latest approved cost

Expenditure

₹707 Cr

Spent to date

Utilization

58.1%

Of revised budget

Escalated

Cost Status

+21.0%

+₹211 Cr increase

Remaining

₹510 Cr

Budget left

Budget Utilization

58.1%
0%25%50%75%100%

Spent

₹707 Cr

Remaining

₹510 Cr

Total

₹1217 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1006 Cr

Revised Cost

₹1217 Cr

Increase

+₹211 Cr

Escalation

+21.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/06/2022

Revised Completion

30/06/2026

Completed

Project Details

Project Code606431
SectorEducation
MinistryDepartment of Higher Education
StateKerala
Data Month2026-08

Financial Summary

Original Cost₹1006 Cr
Revised Cost₹1217 Cr
Expenditure₹707 Cr
Original End Date07/06/2022
Revised Date30/06/2026

Project Intelligence

Cost has increased by ₹211 Cr (21.0%) from the original estimate of ₹1006 Cr.

Expenditure stands at ₹707 Cr, which is 58.1% of the revised project cost.

Remaining budget: ₹510 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHASE 1A is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹1006.00 Cr, later revised to ₹1217.40 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHASE 1A"?
CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHASE 1A is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Kerala. Original cost: ₹1006 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1006 Cr and has been revised to ₹1217 Cr — a cost overrun of +21%. Expenditure to date: ₹707 Cr (58.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHAS is under the Department of Higher Education in the Education sector. Project code: 606431. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. CONSTRUCTION OF PERMANENT CAMPUS FOR IIT PALAKKAD UNDER PHAS is one of several Bihar projects tracked under the Education sector on the IPM system.