Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Construction of Permanent Campus for IIM Jammu Pha
EducationIPM · Central Project +17.9% Overrun#602098

Construction of Permanent Campus for IIM Jammu Phase-1 at Jagti, Nagrota, Jammu, J&K

Department of Higher EducationJammu & KashmirData: 2026-05
Revised Cost: ₹501 CrUtilization: 96.7%Overrun: +₹76 Cr

Original Cost

₹425 Cr

Baseline estimate

+18%

Revised Cost

₹501 Cr

Latest approved cost

Expenditure

₹485 Cr

Spent to date

Utilization

96.7%

Of revised budget

Escalated

Cost Status

+17.9%

+₹76 Cr increase

Remaining

₹16 Cr

Budget left

Budget Utilization

96.7%
0%25%50%75%100%

Spent

₹485 Cr

Remaining

₹16 Cr

Total

₹501 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹425 Cr

Revised Cost

₹501 Cr

Increase

+₹76 Cr

Escalation

+17.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2023

Revised Completion

30/11/2025

Completed

Project Details

Project Code602098
SectorEducation
MinistryDepartment of Higher Education
StateJammu & Kashmir
Data Month2026-05

Financial & Timeline

Original Cost₹425 Cr
Revised Cost₹501 Cr
Expenditure₹485 Cr
Original End Date30/06/2023
Revised Date30/11/2025

Project Intelligence

Cost has increased by ₹76 Cr (17.9%) from the original estimate of ₹425 Cr.

Expenditure stands at ₹485 Cr, which is 96.7% of the revised project cost.

Remaining budget: ₹16 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

Frequently Asked Questions

What is IPM project "Construction of Permanent Campus for IIM Jammu Phase-1 at Jagti, Nagrota, Jammu,"?
Construction of Permanent Campus for IIM Jammu Phase-1 at Jagti, Nagrota, Jammu, J&K is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Jammu & Kashmir. Original cost: ₹425 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost was ₹425 Cr and has been revised to ₹501 Cr — a cost overrun of +17.9%. Expenditure to date: ₹485 Cr (96.7% of revised cost). Data as of 2026-05.
Which ministry is responsible for this project?
Construction of Permanent Campus for IIM Jammu Phase-1 at Ja is under the Department of Higher Education in the Education sector. Project code: 602098. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Permanent Campus for IIM Jammu Phase-1 at Ja is one of several Bihar projects tracked under the Education sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview