Original Cost
₹425 Cr
Baseline estimate
Revised Cost
₹501 Cr
Latest approved cost
Expenditure
₹485 Cr
Spent to date
Utilization
96.7%
Of revised budget
Cost Status
+17.9%
+₹76 Cr increase
Remaining
₹16 Cr
Budget left
Spent
₹485 Cr
Remaining
₹16 Cr
Total
₹501 Cr
Original Cost
₹425 Cr
Revised Cost
₹501 Cr
Increase
+₹76 Cr
Escalation
+17.9%
Project Approved
Construction / Implementation
Original End Date
30/06/2023
Revised Completion
30/11/2025
Completed
Cost has increased by ₹76 Cr (17.9%) from the original estimate of ₹425 Cr.
Expenditure stands at ₹485 Cr, which is 96.7% of the revised project cost.
Remaining budget: ₹16 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.