Aviation & Aviation InfrastructureIPM · Central Project#701128

Construction of New Integrated Passenger Terminal Building at Udaipur Airport

Ministry of Civil AviationRajasthan
Revised Cost: ₹887 CrUtilization: 66.4%

Original Cost

₹887 Cr

Baseline estimate

On budget

Revised Cost

₹887 Cr

Latest approved cost

Expenditure

₹589 Cr

Spent to date

Utilization

66.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹298 Cr

Budget left

Budget Utilization

66.4%
0%25%50%75%100%

Spent

₹589 Cr

Remaining

₹298 Cr

Total

₹887 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/03/2026

Revised Completion

26/09/2026

Completed

Project Details

Project Code701128
SectorAviation & Aviation Infrastructure
MinistryMinistry of Civil Aviation
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹887 Cr
Revised Cost₹887 Cr
Expenditure₹589 Cr
Original End Date10/03/2026
Revised Date26/09/2026

Project Intelligence

Project is within original budget of ₹887 Cr — no cost escalation recorded.

Expenditure stands at ₹589 Cr, which is 66.4% of the revised project cost.

Remaining budget: ₹298 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.

Construction of New Integrated Passenger Terminal Building at Udaipur Airport is a centrally-funded infrastructure project under Ministry of Civil Aviation, in the Aviation & Aviation Infrastructure sector. The original approved cost is ₹887.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of New Integrated Passenger Terminal Building at Udaipur Airport"?
Construction of New Integrated Passenger Terminal Building at Udaipur Airport is a centrally-funded infrastructure project under the Ministry of Civil Aviation, tracked through the Investment Project Monitoring (IPM) system. Sector: Aviation & Aviation Infrastructure. State: Rajasthan. Original cost: ₹887 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹887 Cr has not been significantly revised. Expenditure: ₹589 Cr (66.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of New Integrated Passenger Terminal Building a is under the Ministry of Civil Aviation in the Aviation & Aviation Infrastructure sector. Project code: 701128. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of New Integrated Passenger Terminal Building a is one of several Bihar projects tracked under the Aviation & Aviation Infrastructure sector on the IPM system.