Original Cost
₹887 Cr
Baseline estimate
Revised Cost
₹887 Cr
Latest approved cost
Expenditure
₹538 Cr
Spent to date
Utilization
60.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹349 Cr
Budget left
Spent
₹538 Cr
Remaining
₹349 Cr
Total
₹887 Cr
Project Approved
Construction / Implementation
Original End Date
10/03/2026
Revised Completion
26/09/2026
Completed
Project is within original budget of ₹887 Cr — no cost escalation recorded.
Expenditure stands at ₹538 Cr, which is 60.7% of the revised project cost.
Remaining budget: ₹349 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Aviation & Aviation Infrastructure. Ministry: Ministry of Civil Aviation.