Original Cost
₹26.4K Cr
Baseline estimate
Revised Cost
₹30.7K Cr
Latest approved cost
Expenditure
₹29.8K Cr
Spent to date
Utilization
97.1%
Of revised budget
Cost Status
+16.2%
+₹4290 Cr increase
Remaining
₹882 Cr
Budget left
Spent
₹29.8K Cr
Remaining
₹882 Cr
Total
₹30.7K Cr
Original Cost
₹26.4K Cr
Revised Cost
₹30.7K Cr
Increase
+₹4290 Cr
Escalation
+16.2%
Project Approved
Construction / Implementation
Original End Date
22/03/2021
Revised Completion
30/09/2026
Completed
Mega infrastructure project worth ₹30.7K Cr — among the largest central projects in Karnataka.
Cost has increased by ₹4290 Cr (16.2%) from the original estimate of ₹26.4K Cr.
Expenditure stands at ₹29.8K Cr, which is 97.1% of the revised project cost.
Remaining budget: ₹882 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Urban Public Transport. Ministry: Ministry of Housing & Urban Affairs.