Original Cost
₹495 Cr
Baseline estimate
Revised Cost
₹430 Cr
Latest approved cost
Expenditure
₹371 Cr
Spent to date
Utilization
86.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹59 Cr
Budget left
Spent
₹371 Cr
Remaining
₹59 Cr
Total
₹430 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2022
Revised Completion
31/10/2026
Completed
Project is within original budget of ₹495 Cr — no cost escalation recorded.
Expenditure stands at ₹371 Cr, which is 86.3% of the revised project cost.
Remaining budget: ₹59 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Education. Ministry: Department of Higher Education.