EducationIPM · Central Project#612885

Construction and Developement of National Institute of Technology Meghalaya Permanent Campus at Sohra

Department of Higher EducationMeghalaya
Revised Cost: ₹430 CrUtilization: 89.7%

Original Cost

₹495 Cr

Baseline estimate

On budget

Revised Cost

₹430 Cr

Latest approved cost

Expenditure

₹385 Cr

Spent to date

Utilization

89.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹44 Cr

Budget left

Budget Utilization

89.7%
0%25%50%75%100%

Spent

₹385 Cr

Remaining

₹44 Cr

Total

₹430 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2022

Revised Completion

31/10/2026

Completed

Project Details

Project Code612885
SectorEducation
MinistryDepartment of Higher Education
StateMeghalaya
Data Month2026-08

Financial Summary

Original Cost₹495 Cr
Revised Cost₹430 Cr
Expenditure₹385 Cr
Original End Date31/03/2022
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹495 Cr — no cost escalation recorded.

Expenditure stands at ₹385 Cr, which is 89.7% of the revised project cost.

Remaining budget: ₹44 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Education. Ministry: Department of Higher Education.

Construction and Developement of National Institute of Technology Meghalaya Permanent Campus at Sohra is a centrally-funded infrastructure project under Department of Higher Education, in the Education sector. The original approved cost is ₹495.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction and Developement of National Institute of Technology Meghalaya Perm"?
Construction and Developement of National Institute of Technology Meghalaya Permanent Campus at Sohra is a centrally-funded infrastructure project under the Department of Higher Education, tracked through the Investment Project Monitoring (IPM) system. Sector: Education. State: Meghalaya. Original cost: ₹495 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹495 Cr and has been revised to ₹430 Cr — a cost overrun of -13.2%. Expenditure to date: ₹385 Cr (89.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction and Developement of National Institute of Techn is under the Department of Higher Education in the Education sector. Project code: 612885. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction and Developement of National Institute of Techn is one of several Bihar projects tracked under the Education sector on the IPM system.