Augmentation of Transformation Capacity by 3x500 MVA, 400/220 KV ICTS [6th-8th] and 1x1500 MVA, 765/400 KV ICT [4th] at Bidar PS [SPV Name- POWERGRID Bidar Augmentation Transmission Limited]
Original Cost
₹288 Cr
Baseline estimate
Revised Cost
₹288 Cr
Latest approved cost
Expenditure
₹43 Cr
Spent to date
Utilization
15.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹245 Cr
Budget left
Budget Utilization
15.0%Spent
₹43 Cr
Remaining
₹245 Cr
Total
₹288 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/06/2027
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹288 Cr — no cost escalation recorded.
Expenditure stands at ₹43 Cr, which is 15.0% of the revised project cost.
Remaining budget: ₹245 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Augmentation of Transformation Capacity by 3x500 MVA, 400/220 KV ICTS [6th-8th] and 1x1500 MVA, 765/400 KV ICT [4th] at Bidar PS [SPV Name- POWERGRID Bidar Augmentation Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹288.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Augmentation of Transformation Capacity by 3x500 MVA, 400/220 KV ICTS [6th-8th] "?
- Augmentation of Transformation Capacity by 3x500 MVA, 400/220 KV ICTS [6th-8th] and 1x1500 MVA, 765/400 KV ICT [4th] at Bidar PS [SPV Name- POWERGRID Bidar Augmentation Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Karnataka. Original cost: ₹288 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹288 Cr has not been significantly revised. Expenditure: ₹43 Cr (15.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Augmentation of Transformation Capacity by 3x500 MVA, 400/22 is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617068. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Augmentation of Transformation Capacity by 3x500 MVA, 400/22 is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.