Transmission & DistributionIPM · Central Project#615342

Augmentation of Transformation Capacity at jam Khambhaliya PS [GIS] [SPV Name POWERGRID Jam Khambhaliya Transmission Limited]

Ministry of PowerGujarat
Revised Cost: ₹329 CrUtilization: 26.0%

Original Cost

₹329 Cr

Baseline estimate

On budget

Revised Cost

₹329 Cr

Latest approved cost

Expenditure

₹86 Cr

Spent to date

Utilization

26.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹243 Cr

Budget left

Budget Utilization

26.0%
0%25%50%75%100%

Spent

₹86 Cr

Remaining

₹243 Cr

Total

₹329 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/07/2026

Revised Completion

30/04/2027

Completed

Project Details

Project Code615342
SectorTransmission & Distribution
MinistryMinistry of Power
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹329 Cr
Revised Cost₹329 Cr
Expenditure₹86 Cr
Original End Date14/07/2026
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹329 Cr — no cost escalation recorded.

Expenditure stands at ₹86 Cr, which is 26.0% of the revised project cost.

Remaining budget: ₹243 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Augmentation of Transformation Capacity at jam Khambhaliya PS [GIS] [SPV Name POWERGRID Jam Khambhaliya Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹329.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Augmentation of Transformation Capacity at jam Khambhaliya PS [GIS] [SPV Name PO"?
Augmentation of Transformation Capacity at jam Khambhaliya PS [GIS] [SPV Name POWERGRID Jam Khambhaliya Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Gujarat. Original cost: ₹329 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹329 Cr has not been significantly revised. Expenditure: ₹86 Cr (26.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Augmentation of Transformation Capacity at jam Khambhaliya P is under the Ministry of Power in the Transmission & Distribution sector. Project code: 615342. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Augmentation of Transformation Capacity at jam Khambhaliya P is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.