Original Cost
₹319 Cr
Baseline estimate
Revised Cost
₹319 Cr
Latest approved cost
Expenditure
₹13 Cr
Spent to date
Utilization
4.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹306 Cr
Budget left
Spent
₹13 Cr
Remaining
₹306 Cr
Total
₹319 Cr
Project Approved
Construction / Implementation
Original End Date
30/03/2028
Revised Completion
Completed
Project is within original budget of ₹319 Cr — no cost escalation recorded.
Expenditure stands at ₹13 Cr, which is 4.0% of the revised project cost.
Remaining budget: ₹306 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.