Construction of Submersible Bridge Including approach Road Across Narmada River on Hirapur Sankal Road in District Narsinghpur in EPC Mode.
Tender Description
Construction of Submersible Bridge Including approach Road Across Narmada River on Hirapur Sankal Road in District Narsinghpur in EPC Mode.
Tender Specifications & Timeline
16 FieldsTotal Bidders
8
Lowest Bid (L1)
₹28.21 Cr
Estimated Value (PAC)
₹40.42 Cr
Margin vs Estimate
-30.21%
Lowest Bidder (L1) · Award pending
Accepted / L1L1 to L2 Spread
+7.29%
Completion Period
730 days
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ₹28.21 Cr | 0.0% (L1) | -30.21% | Accepted / L1 | |
| L2 | Vindhya Construction Company#1484574 | ₹30.27 Cr | +7.29% | Rejected-Fin | Rejected-Fin |
| L3 | ₹31.72 Cr | +12.44% | Rejected-Fin | Rejected-Fin | |
| L4 | SUNDRANI CONSTRUCTION Co.#1483729 | ₹33.90 Cr | +20.17% | Rejected-Fin | Rejected-Fin |
| L5 | Aanuj Infraprojects Pvt. Ltd..#1453486 | ₹34.92 Cr | +23.79% | Rejected-Fin | Rejected-Fin |
| L6 | ₹34.94 Cr | +23.86% | Rejected-Fin | Rejected-Fin | |
| L7 | ₹35.45 Cr | +25.66% | Rejected-Fin | Rejected-Fin | |
| L8 | Harjasrai Varialdas#1483247 | ₹38.41 Cr | +36.17% | Rejected-Fin | Rejected-Fin |
This bridges tender covers construction of Submersible Bridge Including approach Road Across Narmada River on Hirapur Sankal Road in District Narsinghpur in EPC Mode. , issued by PWD- Roads and Bridges under reference 29/2025-26. The estimated contract value is ₹40.42 Cr, and the tender is currently Expired. Under financial bid evaluation, RAJESH SHARMA INFRASTRUCTURE DEVELOPERS PRIVATE LIMITED emerged as the lowest (L1) bidder with a quoted bid amount of ₹28.21 Cr.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Narsinghpur. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Higher Rate Quoted then L1
Higher Rate Quoted then L1
Higher Rate Quoted then L1
Higher Rate Quoted then L1
Lowest Rate Quoted By Contractor
Higher Rate Quoted then L1
Higher Rate Quoted then L1
Higher Rate Quoted then L1
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Aanuj Infraprojects Pvt Ltd #1453486 | 22-Apr-2026 02:42 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 349200000.000 | L5 | Higher Rate Quoted then L1 |
HARJASRAI VARIALDAS #1483247 | 22-Apr-2026 03:39 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 384133000.000 | L8 | Higher Rate Quoted then L1 |
K.G.Gupta Infrastructure Pvt. Ltd. #1476285 | 22-Apr-2026 04:16 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 354500000.000 | L7 | Higher Rate Quoted then L1 |
PRL PROJECTS AND INFRASTRUCTURE LIMITED #1485709 | 22-Apr-2026 05:10 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 349400000.000 | L6 | Higher Rate Quoted then L1 |
RAJESH SHARMA INFRASTRUCTURE DEVELOPERS PRIVATE LIMITED #1483931 | 22-Apr-2026 03:57 PM | Accepted-Finance Updated: 25-Aug-2026 04:35 PM | 282100000.000 | L1 | Lowest Rate Quoted By Contractor |
SUNDRANI CONSTRUCTION CO #1483729 | 22-Apr-2026 03:51 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 339000000.000 | L4 | Higher Rate Quoted then L1 |
VIJAY KUMAR MISHRA CONSTRUCTION PVT LTD #1485415 | 22-Apr-2026 05:12 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 317200000.000 | L3 | Higher Rate Quoted then L1 |
vindhya construction company #1484574 | 22-Apr-2026 04:18 PM | Rejected-Finance Updated: 25-Aug-2026 04:35 PM | 302670000.000 | L2 | Higher Rate Quoted then L1 |
Bid Evaluation Details & Logs
technical bid opening
Date: 27-Apr-2026 04:04 PM
Officer: PREM CHANDRA VERMA
Bid opening summary
technical evaluation
Date: 17-Aug-2026 04:23 PM
Officer: Preeti Dinker More
finance bid opening
Date: 18-Aug-2026 03:15 PM
Officer: SANJAY KUMAR
Construction of Submersible Bridge Including approach Road Across Narmada River on Hirapur Sankal Road in District Narsinghpur in EPC Mode.
finance evaluation
Date: 25-Aug-2026 04:35 PM
Officer: Preeti Dinker More
About This Procurement Notice
This Madhya Pradesh state government tender was issued by PWD- Roads and Bridges. The estimated contract value is ₹40.42 Cr. Bids must be submitted by 22-Apr-2026 05:30 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of Submersible Bridge Including approach Road Across Narmada River "?
- The current status of this tender is "Expired". The submission deadline is 22-Apr-2026 05:30 PM. This information is sourced from official government procurement portals.
- QWho issued this Madhya Pradesh government tender?
- This tender was issued by PWD- Roads and Bridges. The reference number is 29/2025-26. It is a Madhya Pradesh state government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹40.42 Cr. This is the approximate contract value as disclosed in the official tender document.
- QWho is the lowest (L1) bidder for this tender?
- Under financial bid evaluation for "Construction of Submersible Bridge Including approach Road Across Narmada River on Hirapur Sankal Road in District Narsinghpur in EPC Mode.", RAJESH SHARMA INFRASTRUCTURE DEVELOPERS PRIVATE LIMITED emerged as the lowest (L1) bidder with a quoted bid amount of ₹28.21 Cr. Full bid rankings and vendor comparisons are available on BiharInfraTales.