MDRRCD BiharOngoning

PR work of Muzaffarpur-Pusa Road in km 1st, 2nd, 3rd, 4th, to 20th, 21st(P) and 22nd to 23rd (P) for the year 2024-25

#902
Road Division Muzaffarpur -1
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹12.22 Cr
Length21.00 km
Start25-07-2025
Completion31-07-2026
MDR · North Wing
Road Division Muzaffarpur -1
MAHESH KUMAR SINGH CONSTRUCTION PRIVATE LIMITED

Project Details

6 Fields
Project No.
902
Wing
North Wing
Division
Road Division Muzaffarpur -1
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
Non Plan

Cost & Timeline

6 Fields
Agreement Value
₹12.22 Cr
Sanctioned Length
21.00 km
Contractor
MAHESH KUMAR SINGH CONSTRUCTION PRIVATE LIMITED
AA Date
21-02-2025
Start Date
25-07-2025
Expected Completion
31-07-2026

PR work of Muzaffarpur-Pusa Road in km 1st, 2nd, 3rd, 4th, to 20th, 21st(P) and 22nd to 23rd (P) for the year 2024-25 is a Bihar Road Construction Department (RCD) project under Road Division Muzaffarpur -1, classified as a MDR. The agreement amount for this project is ₹12.22 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work in Progress.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "PR work of Muzaffarpur-Pusa Road in km 1st, 2nd, 3rd, 4th, to 20th, 21st(P) and "?
Status: Ongoning. This MDR project under Road Division Muzaffarpur -1 (North Bihar Road Circle Muzaffarpur) covers 21.00 km of road work. Expected completion: 31-07-2026.
QWho is the contractor for RCD project 902?
The contractor for this project is MAHESH KUMAR SINGH CONSTRUCTION PRIVATE LIMITED. Project number: 902. Division: Road Division Muzaffarpur -1. Administrative approval date: 21-02-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "PR work of Muzaffarpur-Pusa Road in km 1st, 2nd, 3rd, 4th, t" is ₹12.22 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Muzaffarpur -1.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 902 "PR work of Muzaffarpur-Pusa Road in km 1st, 2nd, 3rd, 4th, t" is one of thousands of road improvement and construction works tracked by BiharInfraTales.