Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Bochaha-Keotsa Raod in 31.4th km (BR23RC-111) / RCPLWE (Length 5x22.84M)

#187
Road Division Muzaffarpur -1
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹5.67 Cr
Length0.11 km
Start12-12-2019
Completion11-06-2021
MDR · North Wing
Road Division Muzaffarpur -1
M/S Royal Engineers, Prop-Chandra Kishore Shahi

Project Details

6 Fields
Project No.
187
Wing
North Wing
Division
Road Division Muzaffarpur -1
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹5.67 Cr
Sanctioned Length
0.11 km
Contractor
M/S Royal Engineers, Prop-Chandra Kishore Shahi
AA Date
15-02-2019
Start Date
12-12-2019
Expected Completion
11-06-2021

Bochaha-Keotsa Raod in 31.4th km (BR23RC-111) / RCPLWE (Length 5x22.84M) is a Bihar Road Construction Department (RCD) project under Road Division Muzaffarpur -1, classified as a MDR. The agreement amount for this project is ₹5.67 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Bridge work completed and approach work in progress. Found. 100% (6/6) Well, Sub Str. 100%, Sup Str 100%, Approach 20 100

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Bochaha-Keotsa Raod in 31.4th km (BR23RC-111) / RCPLWE (Length 5x22.84M)"?
Status: Completed. This MDR project under Road Division Muzaffarpur -1 (North Bihar Road Circle Muzaffarpur) covers 0.11 km of road work. Expected completion: 11-06-2021.
QWho is the contractor for RCD project 187?
The contractor for this project is M/S Royal Engineers, Prop-Chandra Kishore Shahi. Project number: 187. Division: Road Division Muzaffarpur -1. Administrative approval date: 15-02-2019.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Bochaha-Keotsa Raod in 31.4th km (BR23RC-111) / RCPLWE (Leng" is ₹5.67 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Muzaffarpur -1.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 187 "Bochaha-Keotsa Raod in 31.4th km (BR23RC-111) / RCPLWE (Leng" is one of thousands of road improvement and construction works tracked by BiharInfraTales.