| Project No. | 629 |
| Wing | North Wing |
| Division | Road Division Muzaffarpur -1 |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | Non Plan |
| Agreement Value | ₹1.77 Cr |
| Sanctioned Length | 0.20 km |
| Contractor | M/S Royal Engineers, Prop-Chandra Kishore Shahi |
| AA Date | 18-05-2023 |
| Start Date | 06-08-2023 |
| Expected Completion | 05-02-2024 |
Approach road work completed Boulder & Geo Bag work in progress.
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Muzaffarpur -1
Visited: 21 Nov 2023"Workdelayed due to Land Acquisition. GSB & WMM work in progress."