MDRRCD BiharOngoning

W/S of Bela Panari road via agni, rally, shivrampur, dhanava to shakir bigha.

#900
Road Division Gaya.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹24.70 Cr
Length12.00 km
Start03-10-2025
Completion31-03-2027
MDR · South Wing
Road Division Gaya.
Dwarika Singh

Project Details

6 Fields
Project No.
900
Wing
South Wing
Division
Road Division Gaya.
Circle
Magadh Road Circle Gaya
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹24.70 Cr
Sanctioned Length
12.00 km
Contractor
Dwarika Singh
AA Date
28-02-2025
Start Date
03-10-2025
Expected Completion
31-03-2027

W/S of Bela Panari road via agni, rally, shivrampur, dhanava to shakir bigha. is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹24.70 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

WMM and DBM work is in progress. 22HP culvert completed and 2 RCC Box culvert completed. Rest 2 CD work is in progress

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "W/S of Bela Panari road via agni, rally, shivrampur, dhanava to shakir bigha."?
Status: Ongoning. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 12.00 km of road work. Expected completion: 31-03-2027.
QWho is the contractor for RCD project 900?
The contractor for this project is Dwarika Singh. Project number: 900. Division: Road Division Gaya.. Administrative approval date: 28-02-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "W/S of Bela Panari road via agni, rally, shivrampur, dhanava" is ₹24.70 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 900 "W/S of Bela Panari road via agni, rally, shivrampur, dhanava" is one of thousands of road improvement and construction works tracked by BiharInfraTales.