Construction of Gaya - Nalanda Road to Bairka via Harli (near Mayapur) Saraiya, Budhdharaiya, Hudrahi Gharaiya, Kobwa road for the year 2018-19. (Package No-BR12RC47)
Project Details
6 FieldsCost & Timeline
6 FieldsConstruction of Gaya - Nalanda Road to Bairka via Harli (near Mayapur) Saraiya, Budhdharaiya, Hudrahi Gharaiya, Kobwa road for the year 2018-19. (Package No-BR12RC47) is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹19.69 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work completed. Note - Due to land dispute, partially work completed in 895 m length (8th km - 140 m DGBM only, 9th km - 105 m WMM only, 10th km - 280 m GSB only, 12th km - 370 m WMM only) & no any work done in 460 m length (14th km - 165 m, 15th km - 205m, 16th km - 75m, 17th km - 15m). However there is old road existing in land disputed portion and that portion is connected & Motorable. Proposal for Descoping of work for road length 1355 m has been submitted to CE,South, RCD, Patna vide SE, Magadh Road Circle letter no-745WE dated 20.07.2022 EOT proposal submitted to CE, South, RCD, Patna vide letter no. 1276 dt. 20.07.2022 of this office. L.A. process is in progress under perpetual lease 2014.
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Construction of Gaya - Nalanda Road to Bairka via Harli (near Mayapur) Saraiya, "?
- Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 21.41 km of road work. Expected completion: 30-06-2022.
- QWho is the contractor for RCD project 293?
- The contractor for this project is M/s Magadh Construction Works. Project number: 293. Division: Road Division Gaya.. Administrative approval date: 15-02-2019.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Construction of Gaya - Nalanda Road to Bairka via Harli (nea" is ₹19.69 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 293 "Construction of Gaya - Nalanda Road to Bairka via Harli (nea" is one of thousands of road improvement and construction works tracked by BiharInfraTales.