MDRRCD BiharCompleted
Widening and Strengthening work of Kalchakra maidan to Maharani road via Sujata bypass road (Total length-0.600 km) in Gaya district under road division No-1, Gaya for the year 2022-2023 (GROUP-01
#671
Road Division Gaya.
Magadh Road Circle Gaya
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹2.88 Cr
Length0.60 km
Start16-11-2023
Completion15-01-2025
MDR · South Wing
Road Division Gaya.
M/S M G CONSTRUCTION AND CO
Project Details
6 FieldsProject No.
671
Wing
South Wing
Division
Road Division Gaya.
Circle
Magadh Road Circle Gaya
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹2.88 Cr
Sanctioned Length
0.60 km
Contractor
M/S M G CONSTRUCTION AND CO
AA Date
17-07-2023
Start Date
16-11-2023
Expected Completion
15-01-2025
Widening and Strengthening work of Kalchakra maidan to Maharani road via Sujata bypass road (Total length-0.600 km) in Gaya district under road division No-1, Gaya for the year 2022-2023 (GROUP-01 is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹2.88 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
construction work completed.
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening and Strengthening work of Kalchakra maidan to Maharani road via Sujata "?
- Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 0.60 km of road work. Expected completion: 15-01-2025.
- QWho is the contractor for RCD project 671?
- The contractor for this project is M/S M G CONSTRUCTION AND CO. Project number: 671. Division: Road Division Gaya.. Administrative approval date: 17-07-2023.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening and Strengthening work of Kalchakra maidan to Mahar" is ₹2.88 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 671 "Widening and Strengthening work of Kalchakra maidan to Mahar" is one of thousands of road improvement and construction works tracked by BiharInfraTales.