Bihar RCD PMIS — Road Project✓ Completed
Agreement₹22.62 Cr
Length20.23 km
Start19-04-2022
Completion31-03-2024
MDR · South Wing
Road Division Gaya.
Mother India Cons. Pvt. Ltd.

Project Details

6 Fields
Project No.
470
Wing
South Wing
Division
Road Division Gaya.
Circle
Magadh Road Circle Gaya
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹22.62 Cr
Sanctioned Length
20.23 km
Contractor
Mother India Cons. Pvt. Ltd.
AA Date
02-02-2022
Start Date
19-04-2022
Expected Completion
31-03-2024

W/S of Jethian to Baluakhandha at Islampur - Sarbahda - Rajgir (SH-71) road via Chakraghati - Bathani - Telari – Charkama including culverts & minor bridges Length – 20.230 km is a Bihar Road Construction Department (RCD) project under Road Division Gaya., classified as a MDR. The agreement amount for this project is ₹22.62 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

work completed in all repect except 3.10 km Road portion comes under Chakra ghati Forest Reserve. Work hampered in anticipation of forest clearance. Application has been uploaded at PARIVESH Portal for Forest Clearence on dated 07.01.2023 and its Single Window No – SW/107187/2022. For Acquaring forest land, Land acquision process in Progress. Higher Authorities has directed to submit De-scope proposal in 3.1 km road length.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "W/S of Jethian to Baluakhandha at Islampur - Sarbahda - Rajgir (SH-71) road via "?
Status: Completed. This MDR project under Road Division Gaya. (Magadh Road Circle Gaya) covers 20.23 km of road work. Expected completion: 31-03-2024.
QWho is the contractor for RCD project 470?
The contractor for this project is Mother India Cons. Pvt. Ltd.. Project number: 470. Division: Road Division Gaya.. Administrative approval date: 02-02-2022.
QWhat is the agreement value for this Bihar road project?
The agreement value for "W/S of Jethian to Baluakhandha at Islampur - Sarbahda - Rajg" is ₹22.62 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Gaya..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 470 "W/S of Jethian to Baluakhandha at Islampur - Sarbahda - Rajg" is one of thousands of road improvement and construction works tracked by BiharInfraTales.