MDRRCD BiharCompleted
W/S of Jaffarpur P.W.D. road to Anandur Kharauni road (0 to 6.83) under PMGSY (RCPLWE) in the district Muzaffarpur for the year 2017-2018 (package NO-BR23RC-92
#454
Road Division Muzaffarpur -1
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹8.12 Cr
Length6.83 km
Start16-11-2018
Completion15-11-2019
MDR · North Wing
Road Division Muzaffarpur -1
Narsingh Singh
Project Details
6 FieldsProject No.
454
Wing
North Wing
Division
Road Division Muzaffarpur -1
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹8.12 Cr
Sanctioned Length
6.83 km
Contractor
Narsingh Singh
AA Date
02-07-2018
Start Date
16-11-2018
Expected Completion
15-11-2019
W/S of Jaffarpur P.W.D. road to Anandur Kharauni road (0 to 6.83) under PMGSY (RCPLWE) in the district Muzaffarpur for the year 2017-2018 (package NO-BR23RC-92 is a Bihar Road Construction Department (RCD) project under Road Division Muzaffarpur -1, classified as a MDR. The agreement amount for this project is ₹8.12 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Road work completed.
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "W/S of Jaffarpur P.W.D. road to Anandur Kharauni road (0 to 6.83) under PMGSY (R"?
- Status: Completed. This MDR project under Road Division Muzaffarpur -1 (North Bihar Road Circle Muzaffarpur) covers 6.83 km of road work. Expected completion: 15-11-2019.
- QWho is the contractor for RCD project 454?
- The contractor for this project is Narsingh Singh. Project number: 454. Division: Road Division Muzaffarpur -1. Administrative approval date: 02-07-2018.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "W/S of Jaffarpur P.W.D. road to Anandur Kharauni road (0 to " is ₹8.12 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Muzaffarpur -1.
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 454 "W/S of Jaffarpur P.W.D. road to Anandur Kharauni road (0 to " is one of thousands of road improvement and construction works tracked by BiharInfraTales.