| Project No. | 450 |
| Wing | North Wing |
| Division | Road Division Dhaka |
| Circle | Road Circle Motihari |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹95.07 Cr |
| Sanctioned Length | 23.22 km |
| Contractor | BABA HANS CONST. PVT. LTD. |
| AA Date | 24-03-2021 |
| Start Date | 08-10-2021 |
| Expected Completion | 28-02-2025 |
Road work completed and Road Furniture work is in progress.
Superintending Engineer quality visit record
Road Circle Motihari · Road Division Dhaka
Visited: 23 Feb 2024"Inspection report of Chailaha (NH-28A) to Bela Nahar (NH-28A) Road km 8.00 to 31.22 km under Road Division, Dhaka"