Construction of Hard shouldering with Paver Block in Raxual adapur chauradano canal road from chainage 13 to 23.875 (total Length 10.875)

#1103
Road Division Dhaka
Road Circle Motihari
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹5.40 Cr
Length10.88 km
Start09-05-2026
Completion02-07-2026
MDR · North Wing
Road Division Dhaka
M/S SIEMENS Construction Corporation

Project Details

6 Fields
Project No.
1103
Wing
North Wing
Division
Road Division Dhaka
Circle
Road Circle Motihari
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹5.40 Cr
Sanctioned Length
10.88 km
Contractor
M/S SIEMENS Construction Corporation
AA Date
01-09-2025
Start Date
09-05-2026
Expected Completion
02-07-2026

Construction of Hard shouldering with Paver Block in Raxual adapur chauradano canal road from chainage 13 to 23.875 (total Length 10.875) is a Bihar Road Construction Department (RCD) project under Road Division Dhaka, classified as a MDR. The agreement amount for this project is ₹5.40 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

work order issued and Earth Work is in Progress

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Construction of Hard shouldering with Paver Block in Raxual adapur chauradano ca"?
Status: Ongoning. This MDR project under Road Division Dhaka (Road Circle Motihari) covers 10.88 km of road work. Expected completion: 02-07-2026.
QWho is the contractor for RCD project 1103?
The contractor for this project is M/S SIEMENS Construction Corporation. Project number: 1103. Division: Road Division Dhaka. Administrative approval date: 01-09-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Construction of Hard shouldering with Paver Block in Raxual " is ₹5.40 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Dhaka.
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 1103 "Construction of Hard shouldering with Paver Block in Raxual " is one of thousands of road improvement and construction works tracked by BiharInfraTales.