Widending and Strengtheing of Sadikpur-Pabhera-Masaurhi road (SH-1) in km 0.00 to 16.30 for the year 2018-19
Project Details
6 FieldsCost & Timeline
6 FieldsWidending and Strengtheing of Sadikpur-Pabhera-Masaurhi road (SH-1) in km 0.00 to 16.30 for the year 2018-19 is a Bihar Road Construction Department (RCD) project under Road Division Patna City., classified as a SH. The agreement amount for this project is ₹181.27 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Road and Bridge Work with approaches completed. CD Work-26 Nos are completed out of 26 No. (Box culvert at ch.5+900(2/33/0) Super structure completed.) After COS2 02Nos. Minor Bridge at ch.13+500 (2x16.9m), ch.(14+500) size(1x14m) & Minor Bridge at ch. 1+370 (3x16.9) are completed,14+700(2x12) L/S Structure completed.R/S Slab work Completed. ( At ch. 2+900(3/2/2)Box culvert in place of3x10m) completed, ch.13+200(3/33/0) Box culvert in place of 2x16.9m work is completed .) 01 Nos. Major Bridge at ch. 11+400 (5x25.66)is completed at punpun river.(Sub-Structure completed, North Side Approach work is completed & South Side Approach work completed ) Drain-4.00 Km
SE Inspection Log
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Patna City.
Visited: 8 Jun 2025"पथ के 5+900 कि0मी0 में 2/33/0 Box Culvert एवं 14+700 कि०मी० में Minor Bridge (2x12m) के Deck Slab Casting का कार्य प्रगति पर है तथा कि०मी० 12वें में पुनपुन नदी पर उच्चस्तरीय पुल का कार्य पूर्ण हो चुका है एवं Approach पथ का कार्य प्रगति पर है। स्थल पर उपस्थित कार्यपालक अभियंता को निदेशित किया गया कि Minor Bridge एवं Box Culvert का बचे हुए कार्य को पूर्ण कराते हुए Approach कार्य को वर्षा ऋतु से पहले कराया जाय।"
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widending and Strengtheing of Sadikpur-Pabhera-Masaurhi road (SH-1) in km 0.00 t"?
- Status: Completed. This SH project under Road Division Patna City. (Central Road Circle Patna.) covers 16.30 km of road work. Expected completion: 20-08-2021.
- QWho is the contractor for RCD project 258?
- The contractor for this project is M/S VAG Buildtech Limited and M/S Sai Engicon & Construction Pvt Ltd (JV).. Project number: 258. Division: Road Division Patna City.. Administrative approval date: 02-11-2018.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widending and Strengtheing of Sadikpur-Pabhera-Masaurhi road" is ₹181.27 Cr. This is a SH project under Bihar Roads Construction Department (RCD) in Road Division Patna City..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 258 "Widending and Strengtheing of Sadikpur-Pabhera-Masaurhi road" is one of thousands of road improvement and construction works tracked by BiharInfraTales.