| Project No. | 890 |
| Wing | South Wing |
| Division | Road Division Patna City. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹20.34 Cr |
| Sanctioned Length | 5.30 km |
| Contractor | MAHESH KUMAR SINGH CONSTRUCTION PRIVATE LIMITED |
| AA Date | 05-03-2025 |
| Start Date | 09-09-2025 |
| Expected Completion | 08-09-2026 |
Agreement done on 09.09.25. Joint inspection for transfer of road has been done along with EE, RWD Barh on dt. 11.10.25. As per Telephonic Discussion with EE, RWD Barh , the NOC is pending in RWD HQ.Progress of work is very slow, Letters to Contractor has been written Vide this Office letter no 3898 Dtd 27.11.2025, Lt no 134 Dtd 14.01.2026, Lt No 364 Dtd 03.02.2026 ,Lt No 808 Dtd 19.03.2026 & lt. no.1106 dt. 12.05.26 to expedite the progress of work.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Patna City.
Visited: 24 Feb 2026"Road inspection was carried out on 24/02/2026. During inspection, the condition of the road and ongoing works were reviewed, and necessary observations/instructions were communicated to the Executive Engineer and Contractor."