MDRRCD BiharCompleted
Turki-Saraiya Road in 5th km (BR23RC-121) / RCPLWE (Length 2x18 M)
#235
Road Division Muzaffarpur -1
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹4.14 Cr
Length0.04 km
Start06-12-2019
Completion06-03-2021
MDR · North Wing
Road Division Muzaffarpur -1
Singh Construction Pvt. Ltd.
Project Details
6 FieldsProject No.
235
Wing
North Wing
Division
Road Division Muzaffarpur -1
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹4.14 Cr
Sanctioned Length
0.04 km
Contractor
Singh Construction Pvt. Ltd.
AA Date
15-02-2019
Start Date
06-12-2019
Expected Completion
06-03-2021
Turki-Saraiya Road in 5th km (BR23RC-121) / RCPLWE (Length 2x18 M) is a Bihar Road Construction Department (RCD) project under Road Division Muzaffarpur -1, classified as a MDR. The agreement amount for this project is ₹4.14 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Foundation:100%, Sub Str.:100%, Sup Str.100%; Approach: 80% Bridge work completed
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Turki-Saraiya Road in 5th km (BR23RC-121) / RCPLWE (Length 2x18 M)"?
- Status: Completed. This MDR project under Road Division Muzaffarpur -1 (North Bihar Road Circle Muzaffarpur) covers 0.04 km of road work. Expected completion: 06-03-2021.
- QWho is the contractor for RCD project 235?
- The contractor for this project is Singh Construction Pvt. Ltd.. Project number: 235. Division: Road Division Muzaffarpur -1. Administrative approval date: 15-02-2019.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Turki-Saraiya Road in 5th km (BR23RC-121) / RCPLWE (Length 2" is ₹4.14 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Muzaffarpur -1.
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 235 "Turki-Saraiya Road in 5th km (BR23RC-121) / RCPLWE (Length 2" is one of thousands of road improvement and construction works tracked by BiharInfraTales.