East Central RailwayIn Progress

Supplying of 50,000.00 cum 50 mm size machine crushed track ballast as per Railway RDSO's specification for B.G. Railway track & loading the same into any type of railway wagons F.O.R. Japla siding for various projects under CAO/Con/North, ECR.

Estimate Cost

₹10.23 Cr

Sanctioned estimate

Tendered Cost

₹9.38 Cr

-8.3% vs estimate

Physical Progress

13%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹9.38 Cr
Progress13%
Started15-10-2024
Target DOC30-07-2026
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Manish Kumar, AEN/Con/Ballast at Pakur

Work Details

5 Fields
Work No.
337
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-52-23-24 / 10114650094556 dt. 02.01.24; Agt. No. ECR/ECRC/Civil/2024/0010 dt. 01.04.2024
Officer in Charge
Indrajit Kumar, CE/C/NW; Mintu Kumar, Secy. to CAO/C/North; Manish Kumar, AEN/Con/Ballast at Pakur
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹10.23 Cr
Tendered Cost
₹9.38 Cr
Physical Progress
13%
Date Started
15-10-2024
Original DOC
01-01-2025
Extended DOC
30-07-2026

Supplying of 50,000.00 cum 50 mm size machine crushed track ballast as per Railway RDSO's specification for B.G. Railway track & loading the same into any type of railway wagons F.O.R. Japla siding for various projects under CAO/Con/North, ECR. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Jyoti Construction And Engineering Private Limited-Begusarai. The tendered cost of the work is ₹9.38 Cr, and it is currently In Progress with physical progress recorded at 13%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Supplying of 50,000.00 cum 50 mm size machine crushed track ballast as per Railw"?
Status: In Progress. This East Central Railway work is being executed by M/s Jyoti Construction And Engineering Private Limited-Begusarai. Physical progress stands at 13%. Current date of completion (DOC): 30-07-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Jyoti Construction And Engineering Private Limited-Begusarai. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-52-23-24 / 10114650094556 dt. 02.01.24; Agt. No. ECR/ECRC/Civil/2024/0010 dt. 01.04.2024. Work started on 15-10-2024.
QWhat is the cost of this railway work?
The tendered cost of "Supplying of 50,000.00 cum 50 mm size machine crushed track " is ₹9.38 Cr (against an estimate of ₹10.23 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supplying of 50,000.00 cum 50 mm size machine crushed track " is one of hundreds of railway works covered.