Supply of portion and welding of 60 kg/52Kg (New/SH,90/72UTS) rail joints by SKV process (25mm gap) on cess/in situ as per IRS specification T-19-1994 with contractor's materials, labour, T&P etc. including welding supervisor complete between Sakri-Nirmali & Jhanjharpur-Laukaha Bazar section in connection with gauge conversion of SKI-NMA & JJP-LKQ section and between Nirmali-Saraigarh section in connection with Nirmali-Saraigarh new line (Kosi Bridge) Project
Estimate Cost
₹5.04 Cr
Sanctioned estimate
Tendered Cost
₹5.37 Cr
+6.5% vs estimate
Physical Progress
70%
Work completed
Status
Overdue
Past target DOC
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsSupply of portion and welding of 60 kg/52Kg (New/SH,90/72UTS) rail joints by SKV process (25mm gap) on cess/in situ as per IRS specification T-19-1994 with contractor's materials, labour, T&P etc. including welding supervisor complete between Sakri-Nirmali & Jhanjharpur-Laukaha Bazar section in connection with gauge conversion of SKI-NMA & JJP-LKQ section and between Nirmali-Saraigarh section in connection with Nirmali-Saraigarh new line (Kosi Bridge) Project is an East Central Railway (ECR) infrastructure work in Bihar, executed by The India Thermit Corporation Ltd. The tendered cost of the work is ₹5.37 Cr, and it is currently Overdue with physical progress recorded at 70%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Supply of portion and welding of 60 kg/52Kg (New/SH,90/72UTS) rail joints by SKV"?
- Status: Overdue (overdue). This East Central Railway work is being executed by The India Thermit Corporation Ltd. Physical progress stands at 70%. Current date of completion (DOC): 20-10-2025.
- QWho is the agency for this Bihar railway project?
- The agency for this work is The India Thermit Corporation Ltd, 84/22, Fazal Ganj, Kanpur-208012.. Acceptance / agreement reference: LOA No. ECR/CAO/Con/WT/E-Tender/North/34/17-18/5836, dated 24.11.17; Agt No. ECR/CAO/Con/WT/Agt/37 dt. 07.02.2018. Work started on 08-01-2019.
- QWhat is the cost of this railway work?
- The tendered cost of "Supply of portion and welding of 60 kg/52Kg (New/SH,90/72UTS" is ₹5.37 Cr (against an estimate of ₹5.04 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Supply of portion and welding of 60 kg/52Kg (New/SH,90/72UTS" is one of hundreds of railway works covered.