East Central RailwayOverdue

Construction of Station building, ORH, Platform, PP Shelter, Subway, approach road, development of circulating area, boundary wall, drain in yard and other misc. work at Areraj Station in connection with construction of Hajipur-Sagauli new rail line project.

Estimate Cost

₹24.65 Cr

Sanctioned estimate

Tendered Cost

₹19.61 Cr

-20.4% vs estimate

Physical Progress

1%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹19.61 Cr
Progress1%
Started01-05-2024
Target DOC01-11-2025
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Vishal Anand, XEN/C/MFP

Work Details

5 Fields
Work No.
119
Agency
GOLLO GROUP OF INDUSTRIES PAPUMPARE DIPHU BALIJAN
PAPUMPARE, Arunachal Pradesh-791123 India
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-73-23-24/10593500102184 dt 01.05.24
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Vishal Anand, XEN/C/MFP
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹24.65 Cr
Tendered Cost
₹19.61 Cr
Physical Progress
1%
Date Started
01-05-2024
Original DOC
01-11-2025
Extended DOC
N/A

Construction of Station building, ORH, Platform, PP Shelter, Subway, approach road, development of circulating area, boundary wall, drain in yard and other misc. work at Areraj Station in connection with construction of Hajipur-Sagauli new rail line project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by GOLLO GROUP OF INDUSTRIES PAPUMPARE DIPHU BALIJAN. The tendered cost of the work is ₹19.61 Cr, and it is currently Overdue with physical progress recorded at 1%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, ORH, Platform, PP Shelter, Subway, approach ro"?
Status: Overdue (overdue). This East Central Railway work is being executed by GOLLO GROUP OF INDUSTRIES PAPUMPARE DIPHU BALIJAN. Physical progress stands at 1%. Current date of completion (DOC): 01-11-2025.
QWho is the agency for this Bihar railway project?
The agency for this work is GOLLO GROUP OF INDUSTRIES PAPUMPARE DIPHU BALIJAN, PAPUMPARE, Arunachal Pradesh-791123 India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-73-23-24/10593500102184 dt 01.05.24. Work started on 01-05-2024.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station building, ORH, Platform, PP Shelter," is ₹19.61 Cr (against an estimate of ₹24.65 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, ORH, Platform, PP Shelter," is one of hundreds of railway works covered.