East Central RailwayOverdue

Construction of Station building, Approach road, Rail Level Platform, PP shed, Circulating area, Retaining wall and other ancillary works, provision of one no. loop and other related P.way works for proposed crossing station at Asanpur Kupha between Saraigarh & Nirmali station in Samastipur division

Estimate Cost

₹9.85 Cr

Sanctioned estimate

Tendered Cost

₹8.14 Cr

-17.4% vs estimate

Physical Progress

80%

Work completed

Status

Overdue

Past target DOC

East Central Railway — CAO (Con)Overdue
Tendered₹8.14 Cr
Progress80%
Started21-11-2023
Target DOC28-02-2026
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG

Work Details

5 Fields
Work No.
79
Agency
PERRON CONSTRUCTION PRIVATE LIMITED Raj Lakshmi
Palace, Sursand Chowk, Sitamarhi-843331 Bihar, India
Acceptance / LOA
LOA No: 00978550073880 Dated: 22/03/2023, CA No. ECR/ECRC/Civil/2023/0038 dt 01.01.24
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Vinod Kumar, AXEN/Con/DBG
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹9.85 Cr
Tendered Cost
₹8.14 Cr
Physical Progress
80%
Date Started
21-11-2023
Original DOC
21-11-2023
Extended DOC
28-02-2026

Construction of Station building, Approach road, Rail Level Platform, PP shed, Circulating area, Retaining wall and other ancillary works, provision of one no. loop and other related P.way works for proposed crossing station at Asanpur Kupha between Saraigarh & Nirmali station in Samastipur division is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s PERRON CONSTRUCTION PRIVATE LIMITED Raj Lakshmi. The tendered cost of the work is ₹8.14 Cr, and it is currently Overdue with physical progress recorded at 80%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work In progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of Station building, Approach road, Rail Level Platform, PP shed, C"?
Status: Overdue (overdue). This East Central Railway work is being executed by M/s PERRON CONSTRUCTION PRIVATE LIMITED Raj Lakshmi. Physical progress stands at 80%. Current date of completion (DOC): 28-02-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s PERRON CONSTRUCTION PRIVATE LIMITED Raj Lakshmi, Palace, Sursand Chowk, Sitamarhi-843331 Bihar, India. Acceptance / agreement reference: LOA No: 00978550073880 Dated: 22/03/2023, CA No. ECR/ECRC/Civil/2023/0038 dt 01.01.24. Work started on 21-11-2023.
QWhat is the cost of this railway work?
The tendered cost of "Construction of Station building, Approach road, Rail Level " is ₹8.14 Cr (against an estimate of ₹9.85 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of Station building, Approach road, Rail Level " is one of hundreds of railway works covered.