East Central RailwayIn Progress

Construction of ROB in lieu of Level Crossing No. 184 at KM 200/36-38 between Majhowlia-Bettiah section.

Work #309
As of June 2026

Estimate Cost

₹51.73 Cr

Sanctioned estimate

Tendered Cost

₹53.06 Cr

+2.6% vs estimate

Physical Progress

35%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹53.06 Cr
Progress35%
Started15-11-2025
Target DOC30-10-2026
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH

Work Details

5 Fields
Work No.
309
Acceptance / LOA
ECR/ECRC/Civil/2024/0022 dated 28.03.2024
Officer in Charge
Sri Indrajit Kumar, CE/C/NW; Sri Ajay Kumar, Dy.CE/C/BTH; Sri Nirmal Shalhata, AEN/Con/II/BTH
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹51.73 Cr
Tendered Cost
₹53.06 Cr
Physical Progress
35%
Date Started
15-11-2025
Original DOC
15-11-2025
Extended DOC
30-10-2026

Construction of ROB in lieu of Level Crossing No. 184 at KM 200/36-38 between Majhowlia-Bettiah section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Dayal Hitech Engineers Pvt. Ltd.. The tendered cost of the work is ₹53.06 Cr, and it is currently In Progress with physical progress recorded at 35%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of ROB in lieu of Level Crossing No. 184 at KM 200/36-38 between Ma"?
Status: In Progress. This East Central Railway work is being executed by Dayal Hitech Engineers Pvt. Ltd.. Physical progress stands at 35%. Current date of completion (DOC): 30-10-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Dayal Hitech Engineers Pvt. Ltd., Patna. Acceptance / agreement reference: ECR/ECRC/Civil/2024/0022 dated 28.03.2024. Work started on 15-11-2025.
QWhat is the cost of this railway work?
The tendered cost of "Construction of ROB in lieu of Level Crossing No. 184 at KM " is ₹53.06 Cr (against an estimate of ₹51.73 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of ROB in lieu of Level Crossing No. 184 at KM " is one of hundreds of railway works covered.