Major Upgradation of Darbhanga Railway Station of Samastipur Division of East Central Railway.
Estimate Cost
₹314.26 Cr
Sanctioned estimate
Tendered Cost
₹335.91 Cr
+6.9% vs estimate
Physical Progress
0.1%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsMajor Upgradation of Darbhanga Railway Station of Samastipur Division of East Central Railway. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Skylark Infra Engineering Pvt. Ltd. - Altis Holding Corpor…. The tendered cost of the work is ₹335.91 Cr, and it is currently In Progress with physical progress recorded at 0.1%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
original_doc raw: 1095 Days
Frequently Asked Questions
- QWhat is the current status of the railway work "Major Upgradation of Darbhanga Railway Station of Samastipur Division of East Ce"?
- Status: In Progress. This East Central Railway work is being executed by M/s Skylark Infra Engineering Pvt. Ltd. - Altis Holding Corpor…. Physical progress stands at 0.1%.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s Skylark Infra Engineering Pvt Ltd - Altis Holding Corporation (Joint Venture), 1/84, Ist Floor, Sadar Bazar, Delhi Cantt, Delhi-110010. Acceptance / agreement reference: LOA No. 10497630105539 dated 15.06.2024. Work started on 24-03-2025.
- QWhat is the cost of this railway work?
- The tendered cost of "Major Upgradation of Darbhanga Railway Station of Samastipur" is ₹335.91 Cr (against an estimate of ₹314.26 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Major Upgradation of Darbhanga Railway Station of Samastipur" is one of hundreds of railway works covered.