Construction of gate lodges, LC approach roads, supplying fabrication and fixing of height gauges, lifting barriers at LC gates, fixing of various sectional boards and other allied work between Harinagar (excluding) to Valmikinagar road station (including) in connection with doubling of NKE-VKNR section.
Estimate Cost
₹7.96 Cr
Sanctioned estimate
Tendered Cost
₹8.13 Cr
+2.1% vs estimate
Physical Progress
70%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of gate lodges, LC approach roads, supplying fabrication and fixing of height gauges, lifting barriers at LC gates, fixing of various sectional boards and other allied work between Harinagar (excluding) to Valmikinagar road station (including) in connection with doubling of NKE-VKNR section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/S Amit Kumar. The tendered cost of the work is ₹8.13 Cr, and it is currently In Progress with physical progress recorded at 70%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of gate lodges, LC approach roads, supplying fabrication and fixing"?
- Status: In Progress. This East Central Railway work is being executed by M/S Amit Kumar. Physical progress stands at 70%. Current date of completion (DOC): 25-05-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/S Amit Kumar, Vijay Nagar, Kankarbagh, Patna-800020. Acceptance / agreement reference: LOA No.- CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-96-19-20 dt. 11.12.2019. Work started on 08-02-2020.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of gate lodges, LC approach roads, supplying fa" is ₹8.13 Cr (against an estimate of ₹7.96 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of gate lodges, LC approach roads, supplying fa" is one of hundreds of railway works covered.