East Central RailwayIn Progress

Construction of foundation, substructure and superstructure of major bridge no. 139, 141, 145, 159, 164, 171, 195, 202, 203 & 213 in connection with doubling between Muzaffarpur-Sagauli section

Estimate Cost

N/A

Sanctioned estimate

Tendered Cost

₹59.59 Cr

Awarded value

Physical Progress

94%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹59.59 Cr
Progress94%
Started10-08-2019
Target DOC10-05-2026
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)

Work Details

5 Fields
Work No.
264
Agency
Acceptance / LOA
ECR/CAO/Con/WT/Agt/73 dated 01.11.2019
Officer in Charge
Indrajit Kumar, CE/C/NW/MHX; Avanish Sonu, Dy CE/C/I/HJP; Sri. Ravi Shankar Singh (AEN/Con/MFP-I)
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
N/A
Tendered Cost
₹59.59 Cr
Physical Progress
94%
Date Started
10-08-2019
Original DOC
16-01-2021
Extended DOC
10-05-2026

Construction of foundation, substructure and superstructure of major bridge no. 139, 141, 145, 159, 164, 171, 195, 202, 203 & 213 in connection with doubling between Muzaffarpur-Sagauli section is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari Construction and Associates Pvt. Ltd.. The tendered cost of the work is ₹59.59 Cr, and it is currently In Progress with physical progress recorded at 94%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of foundation, substructure and superstructure of major bridge no. "?
Status: In Progress. This East Central Railway work is being executed by Hari Construction and Associates Pvt. Ltd.. Physical progress stands at 94%. Current date of completion (DOC): 10-05-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Hari Construction and Associates Pvt. Ltd., Keshawe, Barauni, Begusarai. Acceptance / agreement reference: ECR/CAO/Con/WT/Agt/73 dated 01.11.2019. Work started on 10-08-2019.
QWhat is the cost of this railway work?
The tendered cost of "Construction of foundation, substructure and superstructure " is ₹59.59 Cr. This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of foundation, substructure and superstructure " is one of hundreds of railway works covered.