East Central RailwayIn Progress

Construction of sub-structure of Major Br. Nos. 15 A, 16 & 17 on well Foundation and Earthwork in filling & Blanketing from Km. 21.000 to Km. 26.185 between Hayaghat-Thalwara stations in connection with SPJ-DBG doubling.

Estimate Cost

₹53.17 Cr

Sanctioned estimate

Tendered Cost

₹57.33 Cr

+7.8% vs estimate

Physical Progress

80%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹57.33 Cr
Progress80%
Started18-01-2023
Target DOC30-06-2026
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ

Work Details

5 Fields
Work No.
16
Agency
Hari Construction and Associates Pvt. Ltd., At. & Po.-Keshawe
P.S.: Barauni, Distt.: Begusarai, Bihar -851134
Acceptance / LOA
ECR/CAO/C/N/ETN/34-18-19 dt 22/02/19 ** ECR/CAO/Con/WT/Agt/55 dt. 28.06.19
Officer in Charge
Mahboob Alam CE/C/NC/MHX; Vinod Kumar Gupta, Dy CE/C/I/SPJ; Vijay Shankar Singh, AEN/C/SPJ
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹53.17 Cr
Tendered Cost
₹57.33 Cr
Physical Progress
80%
Date Started
18-01-2023
Original DOC
21-02-2020
Extended DOC
30-06-2026

Construction of sub-structure of Major Br. Nos. 15 A, 16 & 17 on well Foundation and Earthwork in filling & Blanketing from Km. 21.000 to Km. 26.185 between Hayaghat-Thalwara stations in connection with SPJ-DBG doubling. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Hari Construction and Associates Pvt. Ltd.. The tendered cost of the work is ₹57.33 Cr, and it is currently In Progress with physical progress recorded at 80%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work In progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of sub-structure of Major Br. Nos. 15 A, 16 & 17 on well Foundation"?
Status: In Progress. This East Central Railway work is being executed by Hari Construction and Associates Pvt. Ltd.. Physical progress stands at 80%. Current date of completion (DOC): 30-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Hari Construction and Associates Pvt. Ltd., At. & Po.-Keshawe, P.S.: Barauni, Distt.: Begusarai, Bihar -851134. Acceptance / agreement reference: ECR/CAO/C/N/ETN/34-18-19 dt 22/02/19 ** ECR/CAO/Con/WT/Agt/55 dt. 28.06.19. Work started on 18-01-2023.
QWhat is the cost of this railway work?
The tendered cost of "Construction of sub-structure of Major Br. Nos. 15 A, 16 & 1" is ₹57.33 Cr (against an estimate of ₹53.17 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of sub-structure of Major Br. Nos. 15 A, 16 & 1" is one of hundreds of railway works covered.