Construction of foundation and sub-structure of major bridge No. 306 at Km 124.129, 316 at Km 126.557, 336 at Km 131.58, 340 at Km 132.884, 347 at Km 135.187, 351 at Km 136.609, 361 at Km 139.075, 365 at Km 140.052 and 379 at Km 144.673 between Areraj-Sagauli in connection with construction of Hajipur-Sagauli New Rail Line project.
Estimate Cost
₹111.38 Cr
Sanctioned estimate
Tendered Cost
₹112.09 Cr
+0.6% vs estimate
Physical Progress
45%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsConstruction of foundation and sub-structure of major bridge No. 306 at Km 124.129, 316 at Km 126.557, 336 at Km 131.58, 340 at Km 132.884, 347 at Km 135.187, 351 at Km 136.609, 361 at Km 139.075, 365 at Km 140.052 and 379 at Km 144.673 between Areraj-Sagauli in connection with construction of Hajipur-Sagauli New Rail Line project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Jyoti Tribeni JV-Patna. The tendered cost of the work is ₹112.09 Cr, and it is currently In Progress with physical progress recorded at 45%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
tendered_cost_crore raw: 112.09 after 2nd variation value 136.65
Frequently Asked Questions
- QWhat is the current status of the railway work "Construction of foundation and sub-structure of major bridge No. 306 at Km 124.1"?
- Status: In Progress. This East Central Railway work is being executed by M/s Jyoti Tribeni JV-Patna. Physical progress stands at 45%. Current date of completion (DOC): 30-09-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s Jyoti Tribeni JV-Patna, A/3 Vivekanand Park, Lane A, SE Patliputra Colony, Patna-800014. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-39-23-24/10552170092848 dt 29.12.2023. Work started on 29-12-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Construction of foundation and sub-structure of major bridge" is ₹112.09 Cr (against an estimate of ₹111.38 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of foundation and sub-structure of major bridge" is one of hundreds of railway works covered.