East Central RailwayIn Progress

Earthwork in embankment from km 85.825 to km 89.20, & part of Kesariya yard, Construction of RUB's no.183,185, 189, 194 and 196, Br. no 193 & 195 Subway at Kesariya station in connection with construction of Hajipur-Sagauli new rail line project.

Estimate Cost

₹46.11 Cr

Sanctioned estimate

Tendered Cost

₹42.76 Cr

-7.3% vs estimate

Physical Progress

74%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹42.76 Cr
Progress74%
Started16-05-2023
Target DOC03-06-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Vikash Anand, XEN/C/MFP

Work Details

5 Fields
Work No.
106
Agency
SINGLA CONSTRUCTIONS LIMITED-CHANDIGARH 1ST FLOOR
SCO 22-23, SECTOR 28C Chandigarh- 160002 Chandigarh, India
Acceptance / LOA
CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-67-22-23/01231990077058 dt 16.05.23
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Vikash Anand, XEN/C/MFP
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹46.11 Cr
Tendered Cost
₹42.76 Cr
Physical Progress
74%
Date Started
16-05-2023
Original DOC
15-04-2024
Extended DOC
03-06-2026

Earthwork in embankment from km 85.825 to km 89.20, & part of Kesariya yard, Construction of RUB's no.183,185, 189, 194 and 196, Br. no 193 & 195 Subway at Kesariya station in connection with construction of Hajipur-Sagauli new rail line project. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s SINGLA CONSTRUCTIONS LIMITED-CHANDIGARH 1ST FLOOR. The tendered cost of the work is ₹42.76 Cr, and it is currently In Progress with physical progress recorded at 74%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

Work in progress

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment from km 85.825 to km 89.20, & part of Kesariya yard, Con"?
Status: In Progress. This East Central Railway work is being executed by M/s SINGLA CONSTRUCTIONS LIMITED-CHANDIGARH 1ST FLOOR. Physical progress stands at 74%. Current date of completion (DOC): 03-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s SINGLA CONSTRUCTIONS LIMITED-CHANDIGARH 1ST FLOOR, SCO 22-23, SECTOR 28C Chandigarh- 160002 Chandigarh, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING/ECR-CAO-C-N-ETN-67-22-23/01231990077058 dt 16.05.23. Work started on 16-05-2023.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment from km 85.825 to km 89.20, & part o" is ₹42.76 Cr (against an estimate of ₹46.11 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment from km 85.825 to km 89.20, & part o" is one of hundreds of railway works covered.