East Central RailwayIn Progress

Earthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road etc from Harsiddhi yard (excl) to Sugauli Yard (incl) in connection with construction Hajipur Sagauli New rail Line project

Work #285
As of June 2026

Estimate Cost

₹198.94 Cr

Sanctioned estimate

Tendered Cost

₹204.65 Cr

+2.9% vs estimate

Physical Progress

58%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹204.65 Cr
Progress58%
Started17-12-2023
Target DOC30-06-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; K K Bharti, AEN/C/Kesaria

Work Details

5 Fields
Work No.
285
Agency
VKJ JPW JV-Korba
Plot No. 14 A-1, Shyama Enclave TP Nagar, Korba-495677, Chhattisgarh, India
Acceptance / LOA
CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-37-23-24/10271780093416 dt 17.12.23
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; K K Bharti, AEN/C/Kesaria
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹198.94 Cr
Tendered Cost
₹204.65 Cr
Physical Progress
58%
Date Started
17-12-2023
Original DOC
17-09-2025
Extended DOC
30-06-2026

Earthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road etc from Harsiddhi yard (excl) to Sugauli Yard (incl) in connection with construction Hajipur Sagauli New rail Line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s VKJ JPW JV-Korba. The tendered cost of the work is ₹204.65 Cr, and it is currently In Progress with physical progress recorded at 58%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 204.65 after 2nd variation value 274.34

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, blanketing work, construction of minor bridges, RUB's &"?
Status: In Progress. This East Central Railway work is being executed by M/s VKJ JPW JV-Korba. Physical progress stands at 58%. Current date of completion (DOC): 30-06-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s VKJ JPW JV-Korba, Plot No. 14 A-1, Shyama Enclave TP Nagar, Korba-495677, Chhattisgarh, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-37-23-24/10271780093416 dt 17.12.23. Work started on 17-12-2023.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, blanketing work, construction of mi" is ₹204.65 Cr (against an estimate of ₹198.94 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing work, construction of mi" is one of hundreds of railway works covered.