Earthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road etc from Harsiddhi yard (excl) to Sugauli Yard (incl) in connection with construction Hajipur Sagauli New rail Line project
Estimate Cost
₹198.94 Cr
Sanctioned estimate
Tendered Cost
₹204.65 Cr
+2.9% vs estimate
Physical Progress
58%
Work completed
Status
In Progress
Current stage
Work Details
5 FieldsCost, Progress & Timeline
6 FieldsEarthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road etc from Harsiddhi yard (excl) to Sugauli Yard (incl) in connection with construction Hajipur Sagauli New rail Line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s VKJ JPW JV-Korba. The tendered cost of the work is ₹204.65 Cr, and it is currently In Progress with physical progress recorded at 58%.
Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.
Remarks
tendered_cost_crore raw: 204.65 after 2nd variation value 274.34
Frequently Asked Questions
- QWhat is the current status of the railway work "Earthwork in embankment, blanketing work, construction of minor bridges, RUB's &"?
- Status: In Progress. This East Central Railway work is being executed by M/s VKJ JPW JV-Korba. Physical progress stands at 58%. Current date of completion (DOC): 30-06-2026.
- QWho is the agency for this Bihar railway project?
- The agency for this work is M/s VKJ JPW JV-Korba, Plot No. 14 A-1, Shyama Enclave TP Nagar, Korba-495677, Chhattisgarh, India. Acceptance / agreement reference: CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-37-23-24/10271780093416 dt 17.12.23. Work started on 17-12-2023.
- QWhat is the cost of this railway work?
- The tendered cost of "Earthwork in embankment, blanketing work, construction of mi" is ₹204.65 Cr (against an estimate of ₹198.94 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
- QWhat railway works are tracked on BiharInfraTales?
- BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing work, construction of mi" is one of hundreds of railway works covered.