East Central RailwayIn Progress

Earthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road & other misc work from Bhopatpur Yard (excl) i.e Km 102.235 to Madhubani yard (incl) i.e Km 114.163 in connection with construction of Hajipur Sagauli New Rail Line project

Estimate Cost

₹94.98 Cr

Sanctioned estimate

Tendered Cost

₹87.94 Cr

-7.4% vs estimate

Physical Progress

74%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹87.94 Cr
Progress74%
Started11-10-2022
Target DOC30-09-2026
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP

Work Details

5 Fields
Work No.
279
Agency
Pragati Construction Consultants-New Delhi
28/12, East Punjabi Bagh, Main Ring Road, New Delhi-110026
Acceptance / LOA
CAO-C-HQ-Eng/ECR-CAO-C-N-ETN-19-22-23 / 01023630063526 dt 11/10/22
Officer in Charge
Indrajeet Kumar, CE/C/NW; Prabhat Kumar, DyCE/C/II/HJP; Raj Kumar Mandal, AEN/C/HJP
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹94.98 Cr
Tendered Cost
₹87.94 Cr
Physical Progress
74%
Date Started
11-10-2022
Original DOC
11-07-2024
Extended DOC
30-09-2026

Earthwork in embankment, blanketing work, construction of minor bridges, RUB's & retaining wall, height gauge, approach road & other misc work from Bhopatpur Yard (excl) i.e Km 102.235 to Madhubani yard (incl) i.e Km 114.163 in connection with construction of Hajipur Sagauli New Rail Line project is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s Pragati Construction Consultants-New Delhi. The tendered cost of the work is ₹87.94 Cr, and it is currently In Progress with physical progress recorded at 74%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

tendered_cost_crore raw: 87.94 after 1st variation 99.88

?

Frequently Asked Questions

QWhat is the current status of the railway work "Earthwork in embankment, blanketing work, construction of minor bridges, RUB's &"?
Status: In Progress. This East Central Railway work is being executed by M/s Pragati Construction Consultants-New Delhi. Physical progress stands at 74%. Current date of completion (DOC): 30-09-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s Pragati Construction Consultants-New Delhi, 28/12, East Punjabi Bagh, Main Ring Road, New Delhi-110026. Acceptance / agreement reference: CAO-C-HQ-Eng/ECR-CAO-C-N-ETN-19-22-23 / 01023630063526 dt 11/10/22. Work started on 11-10-2022.
QWhat is the cost of this railway work?
The tendered cost of "Earthwork in embankment, blanketing work, construction of mi" is ₹87.94 Cr (against an estimate of ₹94.98 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Earthwork in embankment, blanketing work, construction of mi" is one of hundreds of railway works covered.