East Central RailwayOverdue

Balance work for construction of station buildings, platforms, gate lodges, PF sheds, approach roads, fixing of different types of boards and other allied works from NKE (excluding) to GAH (Including) in connection with gauge conversion of Narkatiaganj-Gaunaha section.

Estimate Cost

₹9.18 Cr

Sanctioned estimate

Tendered Cost

₹10.00 Cr

+8.9% vs estimate

Physical Progress

90%

Work completed

Status

Overdue

Current stage

East Central Railway — CAO (Con)Overdue
Tendered₹10.00 Cr
Progress90%
Started11-06-2020
Target DOC31-03-2026
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE

Work Details

5 Fields
Work No.
135
Acceptance / LOA
LOA No.- CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-82-19-20/01052380011396
Officer in Charge
Indrajeet Kumar CE/C/NW/MHX; Kumar Sanu Raj, Dy. CE/Con/SMI; Milan Kumar AEN/C/NKE
Report Period
March 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹9.18 Cr
Tendered Cost
₹10.00 Cr
Physical Progress
90%
Date Started
11-06-2020
Original DOC
31-03-2026
Extended DOC
N/A

Balance work for construction of station buildings, platforms, gate lodges, PF sheds, approach roads, fixing of different types of boards and other allied works from NKE (excluding) to GAH (Including) in connection with gauge conversion of Narkatiaganj-Gaunaha section. is an East Central Railway (ECR) infrastructure work in Bihar, executed by Sidhu Enterprises Sir Ganeshdutt Nagar Road No. 4 Bhagwanpur M…. The tendered cost of the work is ₹10.00 Cr, and it is currently Overdue with physical progress recorded at 90%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

Remarks

DOC under process

?

Frequently Asked Questions

QWhat is the current status of the railway work "Balance work for construction of station buildings, platforms, gate lodges, PF s"?
Status: Overdue. This East Central Railway work is being executed by Sidhu Enterprises Sir Ganeshdutt Nagar Road No. 4 Bhagwanpur M…. Physical progress stands at 90%. Current date of completion (DOC): 31-03-2026.
QWho is the agency for this Bihar railway project?
The agency for this work is Sidhu Enterprises Sir Ganeshdutt Nagar Road No. 4 Bhagwanpur Muzaffarpur-842001. Acceptance / agreement reference: LOA No.- CAO-C-HQ-Engineering/ECR-CAO-C-N-ETN-82-19-20/01052380011396. Work started on 11-06-2020.
QWhat is the cost of this railway work?
The tendered cost of "Balance work for construction of station buildings, platform" is ₹10.00 Cr (against an estimate of ₹9.18 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Balance work for construction of station buildings, platform" is one of hundreds of railway works covered.