East Central RailwayIn Progress

Construction of 4 Nos. additional platforms, full length Goods shed with wharf, bridges, ART/ARME siding with pathway, earthwork and blanket works for new lines, shifting of LC No. 31 Spl. and other associated Civil works in connection with yard remodelling of Saharsa Yard.

Work #262
As of June 2026

Estimate Cost

₹61.73 Cr

Sanctioned estimate

Tendered Cost

₹52.43 Cr

-15.1% vs estimate

Physical Progress

15%

Work completed

Status

In Progress

Current stage

East Central Railway — CAO (Con)In Progress
Tendered₹52.43 Cr
Progress15%
Started22-09-2025
Target DOC30-06-2027
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Sunil Kumar, AXEN/Con/SHC

Work Details

5 Fields
Work No.
262
Agency
A S Builders-Delhi
38-A LIG DDA Flats Motia Khan, Delhi-110055
Acceptance / LOA
LOA No. CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-01-25-26 / 01076650135541 dated 31.07.2025.4
Officer in Charge
Mahboob Alam, CE/C/NC/MHX; Mantu Kumar, Dy CE/C/IV/SPJ; Sunil Kumar, AXEN/Con/SHC
Report Period
June 2026

Cost, Progress & Timeline

6 Fields
Estimate Cost
₹61.73 Cr
Tendered Cost
₹52.43 Cr
Physical Progress
15%
Date Started
22-09-2025
Original DOC
30-06-2027
Extended DOC
N/A

Construction of 4 Nos. additional platforms, full length Goods shed with wharf, bridges, ART/ARME siding with pathway, earthwork and blanket works for new lines, shifting of LC No. 31 Spl. and other associated Civil works in connection with yard remodelling of Saharsa Yard. is an East Central Railway (ECR) infrastructure work in Bihar, executed by M/s A S Builders-Delhi. The tendered cost of the work is ₹52.43 Cr, and it is currently In Progress with physical progress recorded at 15%.

Railway works like this — road over/under bridges, station buildings, track linking and allied civil works — are monitored by the CAO (Construction) office of East Central Railway. Other works by the same agency are listed below.

?

Frequently Asked Questions

QWhat is the current status of the railway work "Construction of 4 Nos. additional platforms, full length Goods shed with wharf, "?
Status: In Progress. This East Central Railway work is being executed by M/s A S Builders-Delhi. Physical progress stands at 15%. Current date of completion (DOC): 30-06-2027.
QWho is the agency for this Bihar railway project?
The agency for this work is M/s A S Builders-Delhi, 38-A LIG DDA Flats Motia Khan, Delhi-110055. Acceptance / agreement reference: LOA No. CAO-C-HQ-ENGINEERING / ECR-CAO-C-N-ETN-01-25-26 / 01076650135541 dated 31.07.2025.4. Work started on 22-09-2025.
QWhat is the cost of this railway work?
The tendered cost of "Construction of 4 Nos. additional platforms, full length Goo" is ₹52.43 Cr (against an estimate of ₹61.73 Cr). This is an East Central Railway (ECR) infrastructure work in Bihar.
QWhat railway works are tracked on BiharInfraTales?
BiharInfraTales tracks East Central Railway (ECR) construction works in Bihar — road over bridges (ROB), road under bridges (RUB), station buildings, track linking, and allied civil works monitored by the CAO (Construction) office. "Construction of 4 Nos. additional platforms, full length Goo" is one of hundreds of railway works covered.