Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55 & km.159.357 to km. 287.86 of NH-57 (Old) (OMT Pkg No. 20)
Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
N/A
Contract value
Length
277.053 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
28146
Aerial captures
Project Progress
Stage
Under O&M through OMT/TOT/O&M Agency at Site
Due Date
18-07-2024
Likely Date
-
Completion
0.0%
Physical Done
Project Timeline
Awarded
19-07-2015
Construction Started
19-07-2015
In Progress
Near Completion
-
Completed
-
Physical vs Financial Progress
Project Details
UPC
N/02023/02002/BR
National Highway
27
Regional Office
RO-Patna
State
Bihar
Mode
OMT
Length
277.053 km
Contractor
SMS-AABS India Tollway Pvt Ltd
Project Stage
Under O&M through OMT/TOT/O&M Agency at Site
Drone Frames
28146 frames
Last Flight
2025-03-26
Cost & Timeline
Awarded Cost
N/A
Capital Cost
₹9.16 Cr
Start Date
19-07-2015
PCOD Date
-
Scheduled Completion
18-07-2024
Likely Completion
-
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 22:14:55
Contractor Profile
SMS-AABS India Tollway Pvt Ltd
Project Intelligence
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 277.053 km on 27, improving regional connectivity.
28146 drone frames uploaded — real-time aerial monitoring is active for this project.
Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55 & km.159.357 to km. 287.86 of NH-57 (Old) (OMT Pkg No. 20) is a National Highways Authority of India (NHAI) project on 27 in Bihar. is currently ongoing with physical progress at 0.0%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
28,146 frames · NHAI surveillance footage · UPC N/02023/02002/BR
Frequently Asked Questions
- What is the current status of the NHAI project "Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55 & km.159.357 to"?
- Current physical progress: 0.0%. Financial progress: 0.0%. Project stage: Under O&M through OMT/TOT/O&M Agency at Site. On schedule. Scheduled completion: 18-07-2024. Likely completion: -.
- Who is the contractor for this NHAI highway project?
- The contractor for Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55 & km.159.357 to km. 287.86 of NH-57 (Old) (OMT Pkg No. 20) is SMS-AABS India Tollway Pvt Ltd. The project is under RO-Patna and covers 277.053 km on 27.
- What is the cost of this NHAI highway project?
- Project cost details are not available in our current drone-monitored data for this stretch.
- What is UPC N/02023/02002/BR in NHAI?
- UPC (Unique Project Code) N/02023/02002/BR refers to "Muzaffarpur-Darbhanga-Purnea Section from km. 0.00 to km. 148.55 & km.159.357 to km. 287.86 of NH-57 (Old) (OMT Pkg No. 20)" — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.