Physical Progress
0.0%
Drone-monitored
Financial Progress
0.0%
Of awarded cost
Awarded Cost
N/A
Contract value
Length
277.053 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
28146
Aerial captures
Stage
Under O&M through OMT/TOT/O&M Agency at Site
Due Date
18-07-2024
Likely Date
-
0.0%
Physical Done
Awarded
19-07-2015
Construction Started
19-07-2015
In Progress
Near Completion
-
Completed
-
UPC
N/02023/02002/BR
National Highway
27
Regional Office
RO-Patna
State
Bihar
Mode
OMT
Length
277.053 km
Contractor
SMS-AABS India Tollway Pvt Ltd
Project Stage
Under O&M through OMT/TOT/O&M Agency at Site
Drone Frames
28146 frames
Last Flight
2025-03-26
Awarded Cost
N/A
Capital Cost
₹9.16 Cr
Start Date
19-07-2015
PCOD Date
-
Scheduled Completion
18-07-2024
Likely Completion
-
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 22:14:55
SMS-AABS India Tollway Pvt Ltd
Physical progress stands at 0.0%. Financial utilization at 0.0%.
Project is on schedule or ahead of planned completion date.
Covers 277.053 km on 27, improving regional connectivity.
28146 drone frames uploaded — real-time aerial monitoring is active for this project.
28,146 frames · NHAI surveillance footage · UPC N/02023/02002/BR