4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27
Physical Progress
99.8%
Drone-monitored
Financial Progress
94.7%
Of awarded cost
Awarded Cost
₹185 Cr
Contract value
Length
2.75 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
271
Aerial captures
Project Progress
Stage
CC Issued & O&M by Construction Agency
Due Date
31-08-2024
Likely Date
15-04-2026
Completion
99.8%
Physical Done
Project Timeline
Awarded
04-03-2022
Construction Started
04-03-2022
In Progress
Near Completion
-
Completed
15-04-2026
Physical vs Financial Progress
Project Details
UPC
N/02022/02005/BR
National Highway
27
Regional Office
RO-Patna
State
Bihar
Mode
EPC
Length
2.75 km
Contractor
ASC Infratech Pvt. Ltd.
Project Stage
CC Issued & O&M by Construction Agency
Drone Frames
271 frames
Last Flight
2026-03-26
Cost & Timeline
Awarded Cost
₹184.90 Cr
Capital Cost
₹325.57 Cr
Start Date
04-03-2022
PCOD Date
-
Scheduled Completion
31-08-2024
Likely Completion
15-04-2026
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 09:21:12
Contractor Profile
ASC Infratech Pvt. Ltd.
Project Intelligence
Construction is 99.8% complete — nearing final stages.
Project is on schedule or ahead of planned completion date.
Covers 2.75 km on 27, improving regional connectivity.
271 drone frames uploaded — real-time aerial monitoring is active for this project.
4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27 is a National Highways Authority of India (NHAI) project on 27 in Bihar. The project has an awarded cost of ₹184.90 Cr and is currently 1 with physical progress at 99.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
271 frames · NHAI surveillance footage · UPC N/02022/02005/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000"?
- Current physical progress: 99.8%. Financial progress: 94.7%. Project stage: CC Issued & O&M by Construction Agency. On schedule. Scheduled completion: 31-08-2024. Likely completion: 15-04-2026.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27 is ASC Infratech Pvt. Ltd.. The project is under RO-Patna and covers 2.75 km on 27.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹184.90 Crore. Total capital cost: ₹325.57 Crore. The project is on 27 in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/02022/02005/BR in NHAI?
- UPC (Unique Project Code) N/02022/02005/BR refers to "4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27" — a National Highway project on 27 in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.